Regarding Unit 10 PGB50BB011 in, last week Wednesday SCT completed the job and doid the pressure test for the tank. AndThe next day SCT charge up the pressure of N2 and water until 6.5 bar, after that it was put back to system operation condition. And uUntil now almost 5 days SCT monitored the system and we never fiound any abnormal the system pressure, for your information I will be attaching the PGB cooling water system pressure trend.
AndWe now we request for Tank No 2 ( 10PGB50BB021) PTW. Please consider fworking continually to work Because SCT consider for manpower charges and an installation work schedule. AndThe thlast installation schedule last time I already sumbmitted to PLP but that time I never geot any comments from PLPthem. And SCT hopes PLP towill release the PTW. If you need any more detail or clarification please arrange a meeting so I willcan explain to PLP.
The text above was approved for publishing by the original author.